Thailand to build 7 new airports

The Department of Airports (DOA) plans to spend 50 billion baht on the development of seven new regional airports in Thailand, in Nakhon Pathom, Bueng Khan, Mukdahan, Kalasin, Phayao, Phatthalung and Satun provinces, reviews DailyNews.
The division needs to boost connectivity and supply extra travel options for Thais and foreign vacationers.
New airports around Thailand’s lesser-known locations have been in the pipeline for years but faced delays because of the pandemic. Now, the division is making good progress.
Secure of the DOA’s price range might be spent on the construction of a 25 billion baht airport in Nakhon Pathom province in central Thailand. Feasibility studies are already complete.
The airport might be constructed on 3,500 rai of land in Bang Len district and Nakhon Chai Sri district, around 50 kilometres away from Bangkok. The airport will sport a 45 x 2,500 metre runway.
The department is completing further Environmental Impact Assessment (EIA) reviews earlier than building begins.
The DOA accomplished the feasibility research for the construction of a three.1 billion baht airport on 2,500 rai of land in Pong Puea and Wisist subdistricts, Mueang district, Bueng Kan province, northeast Thailand.
The airport will be situated around 12 kilometres from the province’s clock tower and a 15 minute drive from town.
Design is underway for a 45 x 2,500 metre runway, and EIA reports and procurement plans are underway. Construction is anticipated to start in 2025 and the airport might be open for service by 2027.
Another Isaan airport. The DOA plans to spend 5 billion baht on the instruction of an airport in Kham Pa Lai subdistrict, Mueang District, Mukdahan province, on round 2,000 rai of land 20 kilometres away from Mukdahan City.
Similarly, EIAs and design plans for the runway and passenger terminals are underway. Construction is anticipated to begin in 2025 and the airport is expected to open for service in 2027.
Feasibility studies are full for the development of a 4.1 billion baht airport in Satun Province in southern Thailand. The DOA says they discovered a suitable location to the northwest of the town covering 2,797 rai of land within the Chebilang subdistrict in the Mueang district.
The procurement course of and EIA stories are underway. Construction is deliberate to start in 2026 and the airport could probably be open for service in 2028.
Feasibility studies are underway for 3 extra airports – Kalasin in northeast Thailand, Phayao in northern Thailand and Phatthalung in southern Thailand.
Locals requested that the two billion baht Isaan airport be called “Sarasin” because it will service each Kalasin and Maha Sarakham provinces.
The DOA set a price range of four.four billion baht for the development of Phayao airport in Dok Kham Tai district, around 18 kilometres from the city, with a forty five x 2,500 metre runway..